G2C LinkDev Action Log

External shared workspace — actions, owners & PMO follow-up only. Internal risks, notes and escalation reasons are never shown on this page, for any viewer.

External · LinkDev view
Open Actions
7
Awaiting LinkDev
3
High Priority
4
Closed (30d)
0

Action Log

7 actions
Action IDDescriptionStreamOwnerStatusPriorityNext StepLast UpdatePMO Follow-up
EXT-G2C-ACT-0021LinkDev to share the revised G2C project plan incorporating the GSB Onboarding service.G2CLLinkDevWaiting for External InputHighPMO to chase LinkDev today; escalate to Steering if not received by EOD.8 JulChasing LinkDev for a response
EXT-G2C-ACT-0022Include the GSB Onboarding service within LinkDev's G2C delivery plan.G2CLLinkDevOpenHighLinkDev to include the service and re-issue the plan.7 JulPMO follow-up
EXT-G2C-ACT-0023Whiteshield to review LinkDev's updated plan once shared.G2CLLinkDevBlockedHighAwait the plan then schedule the WS review within 24h.8 JulBlocked — chasing LinkDev
EXT-G2C-ACT-0024Confirm the USP QC environment is ready for G2C testing.G2CLLinkDevWaiting for External InputMediumLinkDev to confirm QC environment availability.8 JulChasing LinkDev for a response
EXT-G2C-ACT-0026Agree the service prioritisation within the recognition set.G2CMBMahmoud BakrOpenMediumPMO to set priority with LinkDev and MoHESR.7 JulPMO follow-up
EXT-ITG-ACT-0025Finalise the technical integration approach for the recognition-set certificate verification service.IntegrationsPHPeter HaddadIn ProgressMediumPMO to confirm and close out.8 JulReady to close — pending PMO confirmation
EXT-ITG-ACT-0029LinkDev to confirm whether the recognition-set integration uses OAuth2 client-credentials or a shared API key, per the confirmed API/integration list.IntegrationsKNKarim NasserWaiting for External InputHighLinkDev to confirm the authentication method by 14 Jul.8 JulChasing LinkDev for a response